Guidance November 2026  •  6 min read  •  By Enisave Solutions
Electrician's hand working on a circuit breaker panel with colour-coded wiring

The Window Closes Earlier Than Most Sites Expect

Many commercial and industrial sites schedule an electrical outage between mid-December and early January, when load is lowest and the work is least disruptive. That outage is the best opportunity of the year to repair terminations, replace failing devices and re-torque connections. It only pays off if the faults are known before it starts, because parts, isolation plans and contractor time all have to be arranged in advance.

There is a catch. A thermographic survey needs the equipment under load, and a shutdown removes the load. The sequence therefore matters: survey before the shutdown, repair during it, and re-scan once load returns.

Live load

survey at 40% of rated load or the highest normal load available (NETA convention)

7 / 30 days

corrective action windows for P2 and P3 findings in Enisave reports

12 months

maximum infrared inspection interval under NFPA 70B (2023); six months for Condition 3 equipment

A Working Sequence

  • Now to the end of November: survey at normal load. Confirm scope, access and safety controls in advance. Panel covers are removed, or infrared windows used, under the site’s electrical safety controls so the camera has line of sight.
  • On report issue: classify and act. An Escalation Flag (ES) means immediate isolation, a P1 is treated as immediate, and a P2 needs corrective action within 7 days. None of these can wait for the shutdown.
  • Before the outage: prepare. Order parts for P3 findings and any P2 not yet closed, agree the isolation plan and decide who signs off each repair. A P3 reported in late November falls due in late December, which is why it fits the shutdown.
  • During the outage: repair and verify. Complete P3 repairs, re-terminate and re-torque flagged connections, and photograph and date each close-out.
  • After restart: re-scan at load. Re-inspection after P1 and P2 repairs is required in Enisave reports, and a scan of the repaired equipment once load is restored confirms the repair rather than assuming it. Treat that scan as the new baseline for the next survey.

Why Summer Load Helps the Survey

For sites with significant cooling or refrigeration load, such as data centres, cold stores, retail and offices, December to February is typically when plant runs hardest. Higher load makes resistive faults easier to see, which supports a survey at or above the load threshold. A site that runs lightly over the holidays will understate faults, which is the other reason to survey before it winds down.

Higher ambient temperature raises absolute temperatures across the board, so findings must be judged by ΔT against a similar component under similar load and against ambient, never by absolute temperature alone. Record enclosure and plant-room temperatures as well, because a failing ventilation or HVAC path can raise component temperatures across a whole board. Cold-room panel surveys also benefit from warm exterior conditions, since the interior-to-exterior ΔT is larger; see our cold room panel article.

What to Bring Into Scope

  • Main and sub-distribution boards, motor control centres, UPS and power factor correction equipment.
  • Generator, changeover and transfer equipment that will be used over the break.
  • Inverters, PV combiner boxes and battery storage, where fitted. See our articles on solar and battery storage and data centres, including what a survey cannot detect in battery systems.
  • Drives and bearings on refrigeration, HVAC and pumping plant; see electrical vs mechanical thermography.

The restart is a risk point too

Equipment that is de-energised and re-energised goes through a thermal cycle, and any connection disturbed during repair is effectively a new connection. Torque-marking terminations during the outage gives a visual check later, but only a scan at load shows whether the joint is performing. A survey is a point-in-time record and cannot see a fault that develops after it.

Close-Out Evidence for Your Insurer

Insurers and, after a loss, claims investigators look at what the operator can demonstrate. For each finding, keep the report, the date and action taken, the contractor’s sign-off and the post-repair re-scan. An unactioned serious finding is a liability rather than a compliance document. Check your policy wording for the survey and renewal requirements that apply to you; our article on what insurers ask for sets out the common expectations.

Book a Pre-Shutdown Survey

Enisave Solutions conducts live-load electrical thermographic surveys across KZN, Gauteng, Western Cape, and Eastern Cape. Book early so findings can be repaired before the outage.